717 East Market Street
The journey through the construction project after the building was purchased in December 2018 is below. The construction plans, interior demolition, and approval process for the building permit finished up in
The architectural plans took a little while, and began in January 2018. The completed version of the construction drawings to submit to the building permit department weren't ready until almost May.
The only thing Possible to do. do in the meantime was demolition. The MEP permits require an active building permit.

















































Building Out NoraeBar
Coordinating each aspect of a construction project is a process that starts wit engaging subcontractors well